400MW Gas Fired Modernization Project Spotlight
A major utility initiated an expansion project to enhance capacity by 400MW, and support Nevada's growing energy demands. The expansion involved adding two new natural gas-fired units and was approved for $353 million
The project received expedited approval from the Public Utilities Commission of Nevada due to the urgent need to increase the state's energy supply. Construction began in 2023 and concluded in 2024 (9 months).

Solutions
Project Management
Owner's Engineering
Procurement & Contract Negotiation
Construction Management
Outcome
>120M Total Cost Savings
Identified and managed 250 risks, opportunities and threats, delivering the project within budget
Shifted train freight and OEM shipment approach, avoiding total delays of over 7.2 months(218 days)
The client retained our technical and project management team long term due to fit and performance, resulting in a 225% scope increase