Provided T&D Project Management of 2400+ projects for a major Midwest to East Coast Utility.
PROJECT BACKGROUND
A large utility plant in the U.S. had a requirement to bring in key consultants for efficient project execution.


CHALLENGES
-
The client requested a key project management within LTIIP and GridMod 365.
SOLUTIONS

-
Under these programs, CEIS provided more than 15 Project Managers, supported by a dedicated supervisor, overseeing 2,400+ projects from initial concept through final energization.
-
Our Transmission team, consisting of 10 professionals, currently oversees approximately 300 active projects focused on modernizing an aging transmission grid.
On the Distribution side, a team of 5 Project Managers manages 200+ projects per PM, supporting FirstEnergy’s Long Term Infrastructure Improvement Plan and ensuring reliable power delivery to homes, businesses, and other critical aspects of daily life.
OUTCOME
-
Performance results reflect this experience: the Transmission team maintains a 98% on-time project completion rate, while the Distribution team consistently delivers projects 85% on time.