Improved Utility Plant Repair Time by Over 40%.
PROJECT BACKGROUND
A large utility plant in the U.S. had a requirement to replace a full Super heater section.
.jpg)

CHALLENGES
-
The client requested a fixed, aggressive outage window.
SOLUTIONS

-
CEIS deployed an integrated team to lead the owner’s engineering, P&S, and field services. We utilized advanced welding and rigorous quality assurance and quality control, including WPS verification.
OUTCOME
-
Completed all pressure part work a full four days ahead of schedule. This allowed for critical path time savings and ensuring a successful, on-time start up including a 40% reduction in repair time.